US regulator sees approval of Boeing 737 by late June

Target means US airlines would likely not have to greatly extend costly cancellations

An aerial photo shows several Boeing 737 MAX airplanes grounded at Boeing Field in Seattle, Washington.
An aerial photo shows several Boeing 737 MAX airplanes grounded at Boeing Field in Seattle, Washington.

The Federal Aviation Administration (FAA) expects to approve Boeing's 737 MAX jet to return to service as soon as late June, representatives of the US air regulator informed members of the United Nations' aviation agency in a private briefing on Thursday, sources told Reuters.

The target, if achieved, means US airlines would likely not have to greatly extend costly cancellations of 737 MAX jets they have already put in place for the peak summer flying season, but the FAA representatives warned that there was no firm timetable to get the planes back in the air.

American Airlines Group, Southwest Airlines and United Airlines suspended 737 MAX flights into July and August after the FAA grounded Boeing's best-selling jet in March following two crashes in the space of five months that together killed 346 people.

FAA and Boeing officials privately briefed members of the International Civil Aviation Organization's (ICAO) governing council in Montreal on the 737 MAX on Thursday, the same day that the FAA's acting administrator Dan Elwell met with international air regulators for eight hours in Fort Worth, Texas.

READ SOME MORE

Laying out a potential schedule for getting the 737 MAX back in the air in the United States goes further than the FAA’s public statements so far.

Elwell declined to answer questions about the private ICAO briefing. “The last thing I want is to put a date out there and then to have anybody, either the FAA, or you or the public drive to the date instead of the end result or the process,” he told Reuters at a briefing with reporters after the Fort Worth meeting, which he called “constructive.”

He repeated previous statements that the FAA will not approve the plane for flight until it has completed a safety analysis, with no set timetable.

The path to getting the 737 MAX back in the air outside the United States remains even more uncertain. Canada and Europe said on Wednesday they would bring back the grounded aircraft on their own terms, not the FAA’s.

Shares of Boeing, the world's largest plane maker, pared earlier losses on Thursday to close down 0.6 per cent at $350.55. The stock has fallen about 17 per cent since the second crash, of an Ethiopian Airlines jet in March, wiping about $40 billion off its market value.

The FAA has said it will not reverse its decision to ground the plane until it sees the findings of a multi-agency review of Boeing’s plan to fix software on the 737 MAX which the plane maker has described as a common link in the two crashes.

Boeing said last week it had completed an update to the software, known as MCAS, which would stop erroneous data from triggering an anti-stall system that automatically turned down the noses of the two planes that crashed, despite pilot efforts to prevent it from doing so.

Boeing has yet to formally submit the fix to the FAA and has not set a date to do so.

“Once we have addressed the information requests from the FAA, we will be ready to schedule a certification test flight and submit final certification documentation,” Boeing communications director Chaz Bickers said on Thursday.

Even after the FAA lifts its ban on 737 MAX flights, airlines will have to spend about 100 and 150 hours getting each aircraft ready to fly again after being put in storage, plus time for training pilots on the new software, officials from the three US airlines that operate the 737 MAX told Reuters.

Southwest, American and United provided estimates to Reuters after discussing the process with Boeing in Miami earlier this week.

FAA associate administrator Ali Bahrami said on Thursday it could take up to a week to return the planes to service following approval, noting that some grounded 737 MAX planes have missed scheduled inspections during the grounding.

On top of that, each airline must train its pilots on the new software.

Boeing has said that simulator training is not necessary for the 737 MAX, and is recommending a mandatory computer-based course that explains MCAS and could be completed at a pilot’s home in about an hour, according to pilot unions.

Elwell said on Thursday that “no individual country stood up and said we need to have sim (simulator) training.” The FAA has made no decision yet on what type of pilot training will be required. Each airline will be responsible for developing its own training plan once the FAA lays down guidelines.

Simulator training remains a “possible option” for Canadian Boeing 737 MAX pilots, but it is too early to say whether it would be mandatory, a Transport Canada official said on Thursday night after the meeting in Fort Worth.

“It would be premature not seeing what Boeing has fully proposed yet to determine if simulator training will in fact be included,” said Nicholas Robinson, the regulator’s director general, civil aviation, told reporters on a conference call.

If the FAA hits its target of approving the 737 MAX to fly by the end of June, airlines may still have to adjust their schedules for the busy summer travel season.

United has removed the MAX from its flight schedule through July 3rd, Southwest through August 5th and American through August 19th.

For Southwest and American, that has meant more than 100 daily flight cancellations during the summer travel season. Both have said they will start using the aircraft as spares if they are ready to fly before those dates. – Reuters