Winter blackouts look to be averted as power plants restored

Surging demand and tight supply sparked fears of electricity cuts

Industry sources expect the plants, at Whitegate in Cork Harbour and Huntstown in north Co Dublin, to restart generating electricity in October and November. Photograph: Christian Hartmann/Reuters
Industry sources expect the plants, at Whitegate in Cork Harbour and Huntstown in north Co Dublin, to restart generating electricity in October and November. Photograph: Christian Hartmann/Reuters

Confidence is growing that two electricity plants will be restored to action in time to stave off the risk of power cuts next winter.

Surging electricity demand combined with tight supplies have sparked fears that power cuts could hit the Republic’s homes and businesses later this year or early in 2022.

Electricity generators in Cork and Dublin that have been out of action for several months are expected to be back on line in time for the winter, considerably lessening any risk of blackouts.

Industry sources expect the plants, at Whitegate in Cork Harbour and Huntstown in north Co Dublin, to restart generating electricity in October and November, in line with schedules already given by their owners.

READ SOME MORE

Bord Gáis Energy has said that it expects Whitegate to restart on November 4th. The company confirmed on Monday that it has "notified the market of its current expectation of Whitegate being offline" until that date.

Energia, one of whose two plants in Huntstown, Co Dublin, has been shut down, has already said that it would be back on line in October.

The return of both plants will restore about 800 megawatts (MW) of electricity to the Republic’s power network, which sources say should be enough to see the system through next winter.

Emergency generators

National Grid operator Eirgrid has dropped a plan to deploy emergency generators in Dublin as a safeguard against power cuts following a legal challenge.

The State company had hired ESB to provide two plants with a total capacity to provide 200MW of electricity.

It is understood that the environment regulator's objections and a legal challenge to the plan by EP UK Investments, owner of Tynagh, Ballylumford and Kilroot power plants, prompted the State company to decide against proceeding.

While sources say the risk to power supplies this winter has largely eased, they warn that there are longer-term fears about energy security as more data centres are built in the Republic.

Eirgird has agreed to connect data centres likely to need 1,800MW of electricity. Developers of facilities with a demand totalling a further 2,000MW have applied for connections. Peak demand in the Republic is 5,500MW.

Legislation obliges the State company to connect data centres. The Commission for Regulation of Utilities launched a consultation on the problem following a warning from Eirgrid that each centre consumed the same amount of power as a sizeable town. Submissions closed in early July.

Sources say data centres pose more of a longer-term problem. According to figures published last year by Eirgrid, data centres now operating in the Republic consume about 1,100MW of electricity.

The likely closure of power plants, including the Republic’s biggest at Moneypoint in Co Clare, is set to compound the problem.

Barry O'Halloran

Barry O'Halloran

Barry O’Halloran covers energy, construction, insolvency, and gaming and betting, among other areas