Johnny Ronan’s 45-storey tower must be refused, council says

An Bord Pleanála has ‘no jurisdiction’ to permit docklands high-rise scheme

Waterfront South Central site, Dublin. Photograph: Naoise Culhane
Waterfront South Central site, Dublin. Photograph: Naoise Culhane

Developer Johnny Ronan must not be granted permission for a 45-storey tower in Dublin's docklands, city council planners have warned An Bord Pleanála.

The council said the board “does not have the jurisdiction to grant permission” for the Waterfront South Central scheme on North Wall Quay, because it contravenes the city development plan and the planning scheme for the docklands.

Mr Ronan last October lost a long-running court battle with the council to secure permission for a 13-storey building further west on the north quays, known as the Salesforce tower, because it exceeded the plan's maximum height rules for the docklands area.

His latest bid to build the city’s tallest building was last month submitted to An Bord Pleanála under the “fast-track” Strategic Housing Development (SHD) process, which bypasses the council’s planning system.

READ SOME MORE

The development would include 1,008 apartments in three blocks – of 14, 41 and 45 storeys – which the Ronan Group said would be a "high-rise, mixed-use garden village in the heart of Dublin's new riverfront district" with "distinctive hanging gardens, green walls and urban forest" that would be a "green lung that will breathe new life into the Dublin Docklands".

National policy

In a letter to the board, the council said the “proposed heights very significantly exceed the maximum planning scheme heights of eight-storey commercial or 10-storey residential. This is a very significant concern.”

In its application to the board, the company maintains the heights are justifiable on the basis of national policy, following the ministerial guidelines issued in December 2018, which remove blanket numerical limitations on height.

A June 2020 legal opinion from Eamon Galligan SC, submitted as part of a pre-application consultation on a different iteration of the proposed development, maintained the board has the power to grant permission for an SHD that “materially contravenes the height provisions” of the council’s planning scheme for the area, “and, by extension, the development plan”.

However, the council said the board has no such jurisdiction to do so. The council has told the board there was nothing in the ministerial guidelines to suggest they were intended to override the planning scheme, rather they required the council to amend its planning scheme to reflect the new guidance on building height.

‘Environmental quality’

The council more than a year ago submitted its proposed amendments to the dockland’s planning scheme but the board has yet to issue its decision.

The application proposed a “significant departure from the development envisioned for the site, and would be an exponential increase in the height, scale and massing of development upon the site without delivering a proportionate improvement in the provision of public open spaces, public realm or active frontages and uses”, the council said.

The council outlined a number of other concerns with the application including a “significant concern with the environmental quality of the proposed open space” and that development was proposed on land “not in the ownership of the applicant”.

The council said it was of the opinion the board “does not have the jurisdiction to grant permission for a development that would materially contravene the Dublin City Council Development Plan”. Therefore, the council said it was “firmly of the opinion that the proposed development does not constitute a reasonable basis for an application and should be rejected”.

A decision on the application is due in May.

*This article was amended on February 28th to correct an error

Olivia Kelly

Olivia Kelly

Olivia Kelly is Dublin Editor of The Irish Times